10/05/2025
[Day 16 | Serian Renovation Project Progress Update]
Strux Construction’s unit renovation project in Serian has reached Day 16, with steady progress on site:
✅ Roof replacement – Completed (100%)
🔧 Partition walls – 80% completed
🔧 Ceiling installation – 50% completed
🧱 Brick wall (toilet) – 80% completed
⏳ Toilet tiling – Not started yet
Our team remains committed to delivering high-quality work on schedule, ensuring each step meets professional standards.