#1. Planning & approval
* Obtain approved shutdown request/work permit.
* Confirm the exact feeder, cable, transformer, RMU/VCB, DB, etc.
* Review SLD and switching schedule.
* Conduct JHA/RA and Toolbox Talk (TBT).
* Notify all affected parties.
2. Identify the circuit
* Physically identify the correct equipment/cable.
* Cross-check equipment ID, feeder number, cable route and SLD.
* Never rely only on labels or drawings.
3. Isolate the supply
* Open the designated circuit breaker/VCB/RMU.
* Isolate all possible sources of supply.
* For systems with back-feed possibilities, check generators, UPS, solar/DG and other incomers.
4. Prevent re-energization
* Apply LOTO (Lock Out/Tag Out) as required.
* Put warning/danger tags.
* Keep the key under the authorized person’s control.
* Barricade the work area where required.
5. Prove dead
* Use an approved, calibrated voltage detector/tester.
* Test the tester → test all phases to phase and phase to earth → test the tester again.
* Confirm zero voltage before proceeding.
6. Discharge and earth
* Discharge stored electrical energy where applicable.
* Apply approved earthing/short-circuiting equipment according to the switching procedure and voltage level.
* For MV/HV work, only authorized/competent personnel should perform this operation.
7. Issue/confirm permit
* The authorized person confirms the isolation, dead condition and earthing.
* Work permit is issued/accepted before work starts.
8. Carry out the work
* Workers follow the approved method statement and permit conditions.
* Maintain required approach distances and PPE.
* Continuously control unauthorized access and possible re-energization.
Restoration after work
1. Complete the work and inspect the installation.
2. Remove tools, materials and temporary connections.
3. Confirm all personnel are clear.
4. Remove temporary earths as per the approved switching sequence.
5. Cancel/close the permit.
6. Remove LOTO only by the authorized person.
7. Energize according to the approved switching schedule.
8. Check voltage, phase sequence, indications, alarms and equipment condition.
9. Record the shutdown/restoration and inform affected parties #