The Sailing Quy Nhơn – Freehold Apartments, Just 200m from the Beach
We would like to update our valued customers on the latest construction progress of the project.
A. Tower A
I. NTH Aluminium & Glass Contractor
1. Office work.
2. Level 34: Corridor plastering.
B. Tower B
1. Basement: Protective plastering for waterproofing of the elevator pit walls.
2. Level 1: Drilling and rebar installation in the ramp and ventilation opening areas.
3. Level 19: Plastering elevator walls and door edges of Apartments 03 and 04 in Hoist Area No. 1.
4. Level 31: Additional masonry work for Apartments 03 and 04 in the hoist area.
5. Level 35: Plastering elevator walls.
6. Levels 38 & 39: Tiling works.
II. Hoàng Gia Waterproofing Contractor
1. Sealant injection on the ground floor.
2. Grinding and finishing of the wastewater treatment tank.
III. HPN Aluminium & Glass Contractor
1. Levels 27–40: Window finishing and installation.
IV. Acotec-VCN Wall Panel Contractor
1. Level 28: Installation of flexible connections.
V. Acon Gypsum Ceiling Contractor
1. Level 25: Installation of ceiling framing systems inside apartments.
2. Level 29: Ceiling panel installation.
VI. Stairwell Defect Repair Team
1. Grinding, patching, and repairing defects on all levels.
VII. Suntech MEP Contractor
1. Plumbing & Drainage System
* Level 4: Positioning, cutting, and chasing for water supply and wall works.
* Level 31: Acoustic insulation installation.
* Level 39: Patching and cleaning.
* Level 40: Drainage pipe installation.
* Level 41: Vent pipe installation.
2. Electrical & Low-Current Systems
* Level 4: Cutting, chasing, and conduit installation.
* Level 21: Conduit installation.
* Levels 25 & 26: Corridor conduit installation.
* Levels 26 & 32: Cable pulling works.
3. Air Conditioning & Ventilation System
* Level 1: Fabrication of copper pipes for Level 38.
* Levels 17 & 18: Patching and repairs.
* Level 21: Nitrogen pressure testing.
* Level 36: Copper pipe installation.
VIII. Fire Protection Contractor – Trường Hải–Liên Việt Joint Venture
1. Fire Alarm System
* Level 30: Removal and installation of fire alarm cables for apartments and corridor exit areas.
2. Firefighting System
* Receiving firefighting pipes.
* Level 36: Installation of corridor firefighting pipes.
Additional Works – Tower B
Finishing Works
* Chiseling, patching, and treating concrete joints beneath the Basement 2 tank for waterproofing of the fire protection water tank.
* Chiseling, patching, and treating concrete joints beneath the circulation tank on Level 5B, as well as formwork removal and concrete repairs.
Structural Works
* Construction of the rigid floor for elevator core CW1.
General
* Cleaning and housekeeping on all floors and around the construction site.